Sylvia Lamb attributes BART service disruptions to aging infrastructure and extreme heat

BART service experienced three days of significant delays and disruptions starting Tuesday due to a fire at a substation near the Daly City station. Sylvia Lamb, the assistant general manager of operations, told the board of directors that the fire was triggered by a failed HVAC unit within a traction power substation that is at least 40 years old. The fire damaged the substation, train control equipment, and a traction power cable, causing the Transbay Tube to be closed for approximately two hours on Tuesday night. The disruptions were also compounded by extreme heat, which caused the system's computers to detect